Trench and In-Ground Cluster Installation
The example photos may take a few min to load.
|
2 - Remove all
organic soil and roots at disposal 3 - Scarify receiving layer to eliminate smearing.
4 - Place
6" of D.O.T. or state highway specification
|
5 - Avoiding
footprints, place In-Drains with painted
stripe facing up,
end to end on sand in trench or bed. |
|
6 - Center
4" perforated
distribution pipe over
9 - Place 12" medium to coarse sand (see step #4) between rows and 6" min. at the sides in trench or bed. (Example: Right) 10 - Complete backfill and loam to 12" min. over In-Drains. Fill should be clean, porous and devoid of large rocks. Use well graded sandy fill with a maximum 10% passing a #200 seive. Do not use wheeled equipment over system. A light track machine may be used with caution, avoiding crushing or shifting of pipe assembly. Backfill in direction of perforated pipe. 11 - Divert surface runoff. Finish grade to prevent surface ponding. Seed loam and protect from erosion. |
7 -Secure pipe with one Eljen clamp per In-Drain. Slide clamp into upfacing core. Force through fabric into sand.
8 - Install Eljen cover fabric over rows of In-Drains. Drape fabric straight down over pipe. Secure with hand shoveled sand. Don't block holes in perforated pipe.
|
![]()
220 Lewiston Road (Rt
#100)
Gray, ME 04039
In
Maine: 1-800-897-4072
Tel: 207-657-2955
Fax: 207-657-2956
wayne@indrain.com